Perry Township Schools

Fast Track Project Schedule

  • $17,926,883

    Contract
  • $1,844,996

    Annual Guaranteed Energy and Operational Savings
  • Oct 2012

    Completion

Project Description

Perry Township Schools was faced with the challenge of renovating the mechanical systems at 12 schools during the short, two-month summer schedule. Project coordination and communication was critical to completing the project before students returned to school.

MSD of Perry Township Logo

“The cooperation and collaboration that Performance Services brought to the table every day was greatly appreciated. This positive atmosphere resulted in a truly enjoyable project experience for everyone involved, a successful end result, and a very pleased Owner.”

Franklin D. Giles

Associate Superintendent

Highlights

  • 2 new additions totaling 18,900 S.F.
  • 17 additional classrooms
  • 313 renovated classrooms with total renovated space of 1,300,000 S.F.
  • Speed of delivery: 9 months
  • Zero incidents safety record

Major Mechanical Equipment

  • 19 boilers
  • 3 chillers
  • 23 pumps
  • 300 ventilation units
  • 1,300 linear feet of fin tube radiation
  • 86 air handler cutovers

Financials

  • Completed on budget
  • No change orders or additional cost to Perry Schools
steve-thoman
Steve Thoman Business Development Manager