School Town of Munster
slideslideslide

Guaranteed Energy Savings Projects Phases I-II

$8,750,000

Total Contract Ph. I-II

$1,231,266

Annual Guaranteed Energy Savings

5

School Buildings

Project Description

In 2016 the School Town of Munster identified a need for energy renovations at several of its school buildings. The District partnered with Performance Services to implement a guaranteed energy savings project. It included a renovation of the Energy Center that serves Munster High School and Wilbur Wright Middle School. After successfully completing this first project, the District recognized it had more work to be done to make their buildings more energy efficient.

The District successfully passed a referendum to fund the additional renovations and worked with Performance Services to implement a second guaranteed energy savings project. Performance Services replaced the High School fieldhouse roof, installed new air conditioning, and began renovations on the varsity locker rooms. This phase also included HVAC renovations and a new secure entry at Frank H. Hammond Elementary School.

Project Highlights

Phase I

Munster High School/Wilbur Wright Middle School Energy Center Renovations

  • Installed new high-efficiency boilers
  • Installed new high-efficiency chiller
  • Energy efficiency improvements to the existing cooling tower

NIPSCO Energy Rebates Earned

  • $56,484

Phase II

Munster High School Fieldhouse Improvements

  • HVAC system replacement, installation of air conditioning
  • Varsity locker room renovations
  • New dimmable LED lighting
  • Roof replacement

Frank H. Hammond Elementary School Improvements

  • Constructed new secure entry
  • Installed new high-efficiency chillers
  • Installed new high-efficiency boilers and water heater

NIPSCO Energy Rebates Earned

  • $68,238

 

Bob Wede


Bob Wede

Business development manager