City of Marshall, TX

Project to Address Deferred Maintenance

  • $13,052,726

    Contract Total
  • 9,669

    Water Meters Installed
  • August 2025

    Completion

Challenge

The City of Marshall, TX faced a critical need to address years of deferred maintenance and aging infrastructure citywide. Key concerns included system-wide water loss due to outdated meter reading systems, inconsistent pressure zones, and distribution leaks. Additionally, the Convention Center was rapidly deteriorating due to a leaking roof, unreliable HVAC systems, and other structural issues. Without intervention, the facility risked further decline, leading to significantly higher repair costs in the future.

Solution

Performance Services partnered with the City of Marshall to implement a comprehensive project that included multiple Utility and Capital Renewal Measures (UCRMs). Key components of the project included:

  • Water Meter Upgrades: Installation of 9,669 smart meters to enhance utility management and data accuracy.
  • Leak Detection: Implementation of advanced leak detection systems to prevent water loss and reduce costs.
  • Convention Center Repairs:
    • Replacement of the leaking roof to protect the facility and extend its lifespan.
    • Upgrades to the HVAC system on the Convention Center roof to ensure reliable and efficient climate control.
    • Modernization of gas piping systems to improve safety and operational efficiency.
    • Stabilization of the foundation to prevent future damage.

Results

The City is on track to have operation and maintenance savings of $4,504,284 over 20 years. Other early outcomes show meaningful results, including:

  • Deferred Maintenance Prevention: The Convention Center’s maintenance issues are being addressed to slow deterioration and avoid more extensive future repairs.
  • Improved Operational Efficiency: Upgraded systems are contributing to more reliable operations and reduced risk.
  • Cost Avoidance: Proactive action has helped the City avoid the higher costs associated with delayed repairs.
  • Collaborative Success: Ongoing communication and engagement with City Council and stakeholders have supported smooth project delivery, even in the face of unforeseen challenges.